Dongyuan Homepage > Encyclopedia of warehouse wall vibrator > Vibration motor technology article >Correct installation sequence and precautions of electromagnetic vibrator

Correct installation sequence and precautions of electromagnetic vibrator

because Electromagnetic vibrator During transportation, the spring hanging device, spring support, motor and other parts are removed and packed separately for delivery. Therefore, the installation must be carried out correctly according to the installation sequence.
 
First of all, check whether the support structure and platform manufacturing are correct. The dimensions and hole spacing of each part should be consistent with the relevant dimensions of the feeder. If the height of the corresponding support is not on the same horizontal plane, the balance must be adjusted.
 
The following is the installation sequence and precautions
 
1) The spring hanging device and the base of the spring support are respectively installed on the bracket;
 
2) Put the suspension spring and support spring in place;
 
3) Assemble the spring gland with the end shaft on the feeding tank body;
 
4) Hang one end of the wire rope on the spring;
 
5) Lift the feeder, and connect the front and rear of the feeding tank with one end of the wire rope or spring support respectively;
 
6) After suspension installation, check the tension of each steel wire rope. The tension of each wire rope should be basically consistent. If it is inconsistent, adjust it. After adjustment, tighten the nut of U-bolt to prevent loosening;
 
7) When installing the motor, it is better to make the center line of the drive shaft of the feeder exciter 10 mm higher than the center line of the motor shaft.
 
8) Otherwise, the clearance between the gate and the gate should not be less than 50 mm.
 
9) Inject proper amount of lubricating oil into the gearbox of vibration exciter.